Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Aug 2023 |
OUT OF 3067 FHTC, 1805 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
17 Aug 2023 |
OUT OF 3067 FHTC, 1805 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
14 Aug 2023 |
OUT OF 3067 FHTC, 1785 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12111.10/13000 pipe laying work is ongoing. 10th & part bill submitted |
Mathilakam AE |
|
10 Aug 2023 |
OUT OF 3067 FHTC, 1773 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12111.10/13000 pipe laying work is ongoing. 10th & part bill submitted |
Mathilakam AE |
|
07 Aug 2023 |
OUT OF 3067 FHTC, 1746 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12111.10/13000 pipe laying work is ongoing. 10th & part bill submitted |
Mathilakam AE |
|
03 Aug 2023 |
OUT OF 3067 FHTC, 1735 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12111.10/13000 pipe laying work is ongoing. 10th & part bill submitted |
Mathilakam AE |
|
31 Jul 2023 |
OUT OF 3067 FHTC, 1735 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12111.10/13000 pipe laying work is ongoing. 10th & part bill submitted |
Mathilakam AE |
|
27 Jul 2023 |
OUT OF 3067 FHTC, 1702 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12111.10/13000 pipe laying work is ongoing. 10th & part bill submitted |
Mathilakam AE |
|
24 Jul 2023 |
OUT OF 3067 FHTC, 1684 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12111.10/13000 pipe laying work is ongoing. 10th & part bill submitted |
Mathilakam AE |
|
20 Jul 2023 |
OUT OF 3067 FHTC, 1668 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12111.10/13000 pipe laying work is ongoing. 10th & part bill submitted |
Mathilakam AE |
|