Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Nov 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6884.5/9000m ,200 mm DI-558.5/623m, 250mm DI-2188.5/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 12th & part bill submitted |
Mathilakam AE |
|
14 Nov 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6884.5/9000m ,200 mm DI-558.5/623m, 250mm DI-2188.5/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 12th & part bill submitted |
Mathilakam AE |
|
10 Nov 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6884.5/9000m ,200 mm DI-558.5/623m, 250mm DI-2188.5/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 12th & part bill submitted |
Mathilakam AE |
|
31 Oct 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
28 Oct 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
21 Oct 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
18 Oct 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
10 Oct 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
05 Oct 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|
02 Oct 2023 |
OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12183.50/13000 pipe laying work is ongoing. 11th & part bill submitted |
Mathilakam AE |
|