Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Dec 2022 OUT OF 3067 FHTC, 653 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing . Mathilakam AE
26 Dec 2022 OUT OF 3067 FHTC, 639 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing . Mathilakam AE
23 Dec 2022 OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing . Mathilakam AE
19 Dec 2022 OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing .4 th and part bill submitted. Mathilakam AE
13 Dec 2022 OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing .4 th and part bill submitted. Mathilakam AE
12 Dec 2022 OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing .4 th and part bill submitted. Mathilakam AE
08 Dec 2022 4 th and part bill submitted. Mathilakam AE
05 Dec 2022 3 rd and part bill submitted Mathilakam AE
05 Dec 2022 OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing Mathilakam AE
03 Dec 2022 OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing Mathilakam AE