Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Dec 2022 |
OUT OF 3067 FHTC, 653 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing . |
Mathilakam AE |
|
26 Dec 2022 |
OUT OF 3067 FHTC, 639 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing . |
Mathilakam AE |
|
23 Dec 2022 |
OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing . |
Mathilakam AE |
|
19 Dec 2022 |
OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing .4 th and part bill submitted. |
Mathilakam AE |
|
13 Dec 2022 |
OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing .4 th and part bill submitted. |
Mathilakam AE |
|
12 Dec 2022 |
OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing .4 th and part bill submitted. |
Mathilakam AE |
|
08 Dec 2022 |
4 th and part bill submitted. |
Mathilakam AE |
|
05 Dec 2022 |
3 rd and part bill submitted |
Mathilakam AE |
|
05 Dec 2022 |
OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing |
Mathilakam AE |
|
03 Dec 2022 |
OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing |
Mathilakam AE |
|