Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Jul 2023 |
OUT OF 3067 FHTC, 1668 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-12111.10/13000 pipe laying work is ongoing. 9th & part bill submitted |
Mathilakam AE |
|
18 Jul 2023 |
OUT OF 3067 FHTC, 1644 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 9th & part bill submitted |
Mathilakam AE |
|
13 Jul 2023 |
OUT OF 3067 FHTC, 1571 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 8th & part bill submitted |
Mathilakam AE |
|
10 Jul 2023 |
OUT OF 3067 FHTC, 1571 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 8th & part bill submitted |
Mathilakam AE |
|
06 Jul 2023 |
OUT OF 3067 FHTC, 1571 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 8th & part bill submitted |
Mathilakam AE |
|
03 Jul 2023 |
OUT OF 3067 FHTC, 1566 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 8th & part bill submitted |
Mathilakam AE |
|
29 Jun 2023 |
OUT OF 3067 FHTC, 1495 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 8th & part bill submitted |
Mathilakam AE |
|
26 Jun 2023 |
OUT OF 3067 FHTC, 1477 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 8th & part bill submitted |
Mathilakam AE |
|
22 Jun 2023 |
OUT OF 3067 FHTC, 1477 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 8th & part bill submitted |
Mathilakam AE |
|
19 Jun 2023 |
OUT OF 3067 FHTC, 1477 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6984.5/9000m ,200 mm DI-558/583m, 250mm DI-2188.5/2529m,350mm DI-1460/1894m,300 mm DI -601.5/623m,400 mm DI-362.5/626 ,50 mm pvc-10292/13000 pipe laying work is ongoing. 8th & part bill submitted |
Mathilakam AE |
|