Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Jan 2024 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. valve chamber work ongoing Mathilakam AE
09 Jan 2024 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. Mathilakam AE
03 Jan 2024 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted. Mathilakam AE
21 Dec 2023 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted Mathilakam AE
18 Dec 2023 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted Mathilakam AE
12 Dec 2023 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted Mathilakam AE
05 Dec 2023 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-7650.97/9000m ,200 mm DI-558.5/623m, 250mm DI-2272.07/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted Mathilakam AE
27 Nov 2023 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6884.5/9000m ,200 mm DI-558.5/623m, 250mm DI-2188.5/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted Mathilakam AE
27 Nov 2023 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6884.5/9000m ,200 mm DI-558.5/623m, 250mm DI-2188.5/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 13th & part bill submitted Mathilakam AE
23 Nov 2023 OUT OF 3067 FHTC, 1818 FHTC COMPLETED, HDPE pipe laying is ongoing 90mm-6884.5/9000m ,200 mm DI-558.5/623m, 250mm DI-2188.5/2529m,350mm DI-1672.1/1894m,300 mm DI -621/623m,400 mm DI-566.7/626 ,50 mm pvc-12183.50/13000,500mm DI - 26/159,pipe laying work is ongoing. 12th & part bill submitted Mathilakam AE