Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Dec 2022 |
OUT OF 3067 FHTC, 617 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3773.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-428.5m pipe laying work is ongoing |
Mathilakam AE |
|
29 Nov 2022 |
OUT OF 3067 FHTC, 597 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3762.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-417.5m pipe laying work is ongoing |
Mathilakam AE |
|
26 Nov 2022 |
OUT OF 3067 FHTC, 597 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3762.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-417.5m pipe laying work is ongoing |
Mathilakam AE |
|
25 Nov 2022 |
OUT OF 3067 FHTC, 597 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3727.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-382.5m pipe laying work is ongoing |
Mathilakam AE |
|
24 Nov 2022 |
OUT OF 3067 FHTC, 597 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3727.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-382.5m pipe laying work is ongoing |
Mathilakam AE |
|
22 Nov 2022 |
OUT OF 3067 FHTC, 597 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3548.6m ,200 mm DI-464.5m,250mm DI-1153.5m,350mm DI-203.5m pipe laying work is ongoing |
Mathilakam AE |
|
21 Nov 2022 |
OUT OF 3067 FHTC, 530 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing |
Mathilakam AE |
|
19 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing |
Mathilakam AE |
|
16 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing |
Mathilakam AE |
|
15 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing |
Mathilakam AE |
|