Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. Mathilakam AE
25 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing (90mm),200 mm DI,250mm DI pipe laying work is ongoing.2nd part bill submitted. Mathilakam AE
21 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing (90mm),200 mm DI,250mm DI pipe laying work is ongoing. Mathilakam AE
18 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing (90mm),200 mm DI pipe laying work is ongoing. Mathilakam AE
17 Oct 2022 200 mm DI pipe laying started Mathilakam AE
17 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),ROW Panchayath submission date 03/10/2022,Panchayath road joint inspection completed on 07/10/2022 Mathilakam AE
14 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),ROW Panchayath submission date 03/10/2022,Panchayath road joint inspection completed on 07/10/2022 Mathilakam AE
13 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),ROW Panchayath submission date 03/10/2022,Panchayath road joint inspection completed on 07/10/2022 Mathilakam AE
13 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),ROW Panchayath submission date 03/10/2022,Panchayath road joint inspection completed on 07/10/2022 Mathilakam AE
12 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),Panchayath road joint inspection completed on 07/10/2022 Mathilakam AE