Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. |
Mathilakam AE |
|
25 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing (90mm),200 mm DI,250mm DI pipe laying work is ongoing.2nd part bill submitted. |
Mathilakam AE |
|
21 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing (90mm),200 mm DI,250mm DI pipe laying work is ongoing. |
Mathilakam AE |
|
18 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing (90mm),200 mm DI pipe laying work is ongoing. |
Mathilakam AE |
|
17 Oct 2022 |
200 mm DI pipe laying started |
Mathilakam AE |
|
17 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),ROW Panchayath submission date 03/10/2022,Panchayath road joint inspection completed on 07/10/2022 |
Mathilakam AE |
|
14 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),ROW Panchayath submission date 03/10/2022,Panchayath road joint inspection completed on 07/10/2022 |
Mathilakam AE |
|
13 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),ROW Panchayath submission date 03/10/2022,Panchayath road joint inspection completed on 07/10/2022 |
Mathilakam AE |
|
13 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),ROW Panchayath submission date 03/10/2022,Panchayath road joint inspection completed on 07/10/2022 |
Mathilakam AE |
|
12 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying started(90mm),Panchayath road joint inspection completed on 07/10/2022 |
Mathilakam AE |
|