Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Oct 2022 | OUT OF 3067 FHTC, 423 FHTC COMPLETED , NHAI Joint inspection completed.HDPE pipe laying started(90mm),DI Pipe supplied | Mathilakam AE | |
10 Oct 2022 | OUT OF 3067 FHTC, 375 FHTC COMPLETED , NHAI Joint inspection completed.HDPE pipe laying started(90mm) | Mathilakam AE | |
06 Oct 2022 | PE Pipe joining and laying | Mathilakam AE | |
03 Oct 2022 | OUT OF 3067 FHTC, 375 FHTC COMPLETED , NHAI Joint inspection completed. | Mathilakam AE | |
30 Sep 2022 | OUT OF 3067 FHTC, 375 FHTC COMPLETED , NHAI Joint inspection completed. | Mathilakam AE | |
29 Sep 2022 | OUT OF 3067 FHTC, 375 FHTC COMPLETED , NHAI Joint inspection completed. | Mathilakam AE | |
27 Sep 2022 | OUT OF 3067 FHTC, 375 FHTC COMPLETED | Mathilakam AE | |
17 Sep 2022 | First and part bill submitted | Mathilakam AE | |
14 Sep 2022 | First and part bill submitted | Mathilakam AE | |
13 Sep 2022 | 205 FHTC COMPLETED , DI pipe supplied | Mathilakam AE |