Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Sep 2022 | 205 FHTC COMPLETED , DI pipe supplied | Mathilakam AE | |
03 Sep 2022 | OUT OF 3067 FHTC , 205 FHTC COMPLETED , DI pipe supplied | Mathilakam AE | |
31 Aug 2022 | OUT OF 3067 FHTC , 205 FHTC COMPLETED , DI pipe supplied | Mathilakam AE | |
27 Aug 2022 | OUT OF 3067 FHTC , 205 FHTC COMPLETED , DI pipe supplied | Mathilakam AE | |
25 Aug 2022 | OUT OF 3067 FHTC , 205 FHTC COMPLETED , DI pipe supplied | Mathilakam AE | |
23 Aug 2022 | OUT OF 3067 FHTC , 205 FHTC COMPLETED , DI pipe supplied | Mathilakam AE | |
22 Aug 2022 | OUT OF 3067 FHTC , 205 FHTC COMPLETED , DI pipe supplied | Mathilakam AE | |
17 Aug 2022 | 350mm,400mm,500mm DI pipe supplied | Mathilakam AE | |
15 Aug 2022 | pipe supplied | Mathilakam AE | |
11 Aug 2022 | pipe supplied | Mathilakam AE |