Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing |
Mathilakam AE |
|
11 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing |
Mathilakam AE |
|
10 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing. |
Mathilakam AE |
|
10 Nov 2022 |
PVC pipe laying work is ongoing,90 mm HDPE Pipe -4240.9 m laid and work on going , Grama panchayath road demand notice issued . |
Mathilakam AE |
|
08 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. |
Mathilakam AE |
|
07 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. |
Mathilakam AE |
|
05 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. |
Mathilakam AE |
|
01 Nov 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. |
Mathilakam AE |
|
31 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. |
Mathilakam AE |
|
29 Oct 2022 |
OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. |
Mathilakam AE |
|