Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Nov 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing Mathilakam AE
11 Nov 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing Mathilakam AE
10 Nov 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-3156.1m ,200 mm DI-464.5m,250mm DI-964.5m pipe laying work is ongoing. Mathilakam AE
10 Nov 2022 PVC pipe laying work is ongoing,90 mm HDPE Pipe -4240.9 m laid and work on going , Grama panchayath road demand notice issued . Mathilakam AE
08 Nov 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. Mathilakam AE
07 Nov 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. Mathilakam AE
05 Nov 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. Mathilakam AE
01 Nov 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. Mathilakam AE
31 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. Mathilakam AE
29 Oct 2022 OUT OF 3067 FHTC, 423 FHTC COMPLETED ,HDPE pipe laying is ongoing 90mm-2177.5m ,200 mm DI-304.5m,250mm DI-198m pipe laying work is ongoing. Mathilakam AE