Status Date Overall Project Status Project Officer Contact
14 Feb 2024 All the works of the scheme are progressing. Anganwadi land for Pulimath panchayath in the scheme not given by Revenue department. Revised AS submitted to KIIFB for PWD road cutting permission and other items. Bridge crossing permission for transmission line laying denied by PWD Bridges. Thiruvananthapuram Project AE3
03 Sep 2023 The access road formation is alternate land of 15.3 LL OHSR at Paramukku is ongoing. KRFB road cutting sanction denied by KRFB for Kilimanoor-Alamcode road, and permission will be given after handing over to PWD Roads Division, Tvpm after DLP period expiring on 30-09-2023. Thiruvananthapuram Project AE3
24 Jul 2023 The alternate OHSR land - 15.3LL OHSR at Paramukku - access road formation by Nagaroor Grama Panchayath is pending. KRFB estimate for permission in Kilimanoor-Alamcode road is pending from KRFB. Thiruvananthapuram Project AE3
28 May 2023 KRFB estimates for Kilimanoor-Alamcode road not yet given. The access pathway to 15.3LL OHSR new land near Thannikonam not yet done by Nagaroor panchayath authorities. Thiruvananthapuram Project AE3
15 Apr 2023 TS approval from KIIFB pending due to which 1st part bill for the work not able to upload in KIIFB PFMS portal. Several reminders with required documents for TS and package approval submitted to KIIFB for approval. Road formation to 15.3 LL OHSR- new site at Thannikonam in Nagaroor panchayath not yet finalized by panchayath authorities. Thiruvananthapuram Project AE3
08 Mar 2023 KIIFB TS file approval pending for the revised amount submitted for approval based on DSR 2018 approved by CE, KWA. Estimate for road restoration not given by KRFB for VC road as discussed in meeting of CE,KIIFB with KRFB and KWA. Access road formation to new 15.3LL OHSR at Nagaroor is yet to be done by Panchayath. Thiruvananthapuram Project AE3
13 Feb 2023 KIIFB package approval given based on the meeting conducted by CEO, KIIFB with KWA and KRFB officials. Thiruvananthapuram Project AE3
27 Jan 2023 KIIFB Package approval file under scrutiny with KIIFB. KRFB road cutting permission not given by KRFB. Relevant documental proof reg. earlier communications of KWA with PWD and KRFB of prior intimation reg. pipe laying in present KRFB stretches submitted to KIIFB for consideration. Revenue land near Altharamoodu-Thannikonam handed over for construction of 15.3LL OHSR (alternate land of Paramukku) by Dist. Collector, TVPM after cancelling the revenue land allotment at Paramukku, formation of access pathway to land directions given to Nagaroor panchayath. Permission not given by Director of Panchayaths for demolishing of Anganwadi at Kuttimoodu WTP land. Other sites handed over to contractor and all sites are clear for construction and pipe laying works. Thiruvananthapuram Project AE3
22 Jan 2023 KIIFB Package approval for the work not given due to pending road cutting permission from KRFB. WTP land-demolishing of Anganwadi building not permitted by panchayath till date, hence work could not be started. Alternate land for Paramukku-15.3 LL OHSR not handed over by Revenue and panchayath. Thiruvananthapuram Project AE3
26 Dec 2022 KIIFB package approval pending due to delay in obtaining KRFB road cutting permission. Work of WTP not started in revenue land, due to delay in permission from Panchayath Director for demolishing of Anganwadi at middle of site. Alternate land for OHSR at Paramukku not handed over by revenue. Thiruvananthapuram Project AE3