Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Sep 2021 |
On enquiry, it was informed that due to Covid-19 spread in office, there is no action taken for the files received in the office. |
Thiruvananthapuram Project AE3 |
|
12 Sep 2021 |
Followed up and enquired at Land transfer section (B-8) at Collectorate, Thiruvananthapuram and Land Revenue Commissonerate regarding transfer of 5 revenue lands. Got information that some clarification which was required regarding 2 revenue lands were received at Commissionerate and further processing is in progress. As per the information recieved from J-6 section at Land Revenue Commissionerate, there is some delay in processing due to the conversion of office files in e-office platform and the digitizing of files is going on. |
Thiruvananthapuram Project AE3 |
|
08 Sep 2021 |
Followed up and enquired at Land transfer section (B-8) at Collectorate, Thiruvananthapuram and Land Revenue Commissonerate regarding transfer of 5 revenue lands. Got information that some clarification which was required regarding 2 revenue lands were received at Commissionerate and further processing is in progress.
As per the information recieved from J-6 section at Land Revenue Commissionerate, there is some delay in processing due to the conversion of office files in e-office platform and the digitizing of files is going on. |
Thiruvananthapuram Project AE3 |
|
05 Sep 2021 |
Land acquisition process is in progress . 19(1) notification issued by Dy. Collector (LA) & LAO for acquisition of 2 Pvt. lands. Revenue land transfer process ongoing in Land Revenue Commissionerate. Land Survey Completed and valuation in progress. Enquired at Land Aquisition wing regarding Advance possession and they conveyed that as Per section 40 of the LARR act Advanced posession clause can be revoked only in case of Natural disaster etc. Out of Five revenue land proposals sent to Land revenue commisonerate two proposals have been returned to Collectorate Land transfer wing asking clarifications regarding an encroachment case for Land at Nellikunnu (Nedumparambu). Remaining revenue land transfer is under process in Land revenue commissionerate. The estimate of the WTP has been submitted after incorporation changes suggested by SE(SR) and SE(PHC) after conducting site visit. |
Thiruvananthapuram Project AE3 |
|
27 Aug 2021 |
Acquisition process is in progress . 19(1) notification issued. Land Survey Completed and valuation in progress. Enquired at Land Aquisition wing regarding Advance possession and they conveyed that as Per section 40 of the LARR act Advanced posession clause can be revoked only in case of Natural disaster etc.Out of Five revenue land proposals sent to Land revenue cmmisonerate two proposal have been returned to Collectorate Land transfer wing asking clarifications regarding an encroachment case for Land at Nellikunnu (Nedumparambu). The estimate of the WTP has been submitted after incorporation changes suggested by SE(SR) and SE(PHC) after conducting site visit. |
Thiruvananthapuram Project AE3 |
|
23 Aug 2021 |
Acquisition process is in progress . 19(1) notification issued. Land Survey Completed and valuation in progress. Enquired at Land Aquisition wing regarding Advance possession and they conveyed that as Per section 40 of the LARR act Advanced posession clause can be revoked only in case of Natural disaster etc.Out of Five revenue land proposals sent to Land revenue cmmisonerate two proposal have been returned to Collectorate Land transfer wing asking clarifications regarding an encroachment case for Land at Nellikunnu (Nedumparambu). The estimate of the WTP has been submitted after incorporation changes suggested by SE(SR) and SE(PHC) after conducting site visit. |
Thiruvananthapuram Project AE3 |
|
16 Aug 2021 |
Acquisition process is in progress . 11(1) notification issued. 19(1) notification awaited. Land Survey Completed and valuation in progress. Enquired at Land Aquisition wing regarding Advance possession and they conveyed that as Per section 40 of the LARR act Advanced posession clause can be revoked only in case of Natural disaster etc Out of Five revenue land proposals sent to Land revenue cmmisonerate two proposal have been returned to Collectorate LAnd transfer wing asking clarifications regarding an encroachment case for Land at Nellikunnu (Nedumparambu) and in case of WTP Land whether land have been allocated to exisitng Anganwadi and Library in same Survey number. The estimate of the WTP has been submitted after incorporation changes suggested by SE(SR) and SE(PHC) after conducting site visit. |
Thiruvananthapuram Project AE3 |
|
14 Aug 2021 |
Acquisition process is in progress . 11(1) notification issued. 19(1) notification awaited. Land Survey Completed and valuation in progress. Enquired at Land Aquisition wing regarding Advance possession and they conveyed that as Per section 40 of the LARR act Advanced posession clause can be revoked only in case of Natural disaster etc Out of Five revenue land proposals sent to Land revenue cmmisonerate two proposal have been returned to Collectorate LAnd transfer wing asking clarifications regarding an encroachment case for Land at Nellikunnu (Nedumparambu) and in case of WTP Land whether land have been allocated to exisitng Anganwadi and Library in same Survey number. The estimate of the WTP has been submitted after incorporation changes suggested by SE(SR) and SE(PHC) after conducting site visit. |
Thiruvananthapuram Project AE3 |
|
12 Aug 2021 |
Acquisition process is in progress . 11(1) notification issued. 19(1) notification awaited. Land Survey Completed and valuation in progress. Enquired at Land Aquisition wing regarding Advance possession and they conveyed that as Per section 40 of the LARR act Advanced posession clause can be revoked only in case of Natural disaster etc Out of Five revenue land proposals sent to Land revenue cmmisonerate two proposal have been returned to Collectorate LAnd transfer wing asking clarifications regarding an encroachment case for Land at Nellikunnu (Nedumparambu) and in case of WTP Land whether land have been allocated to exisitng Anganwadi and Library in same Survey number. The estimate of the WTP has been submitted after incorporation changes suggested by SE(SR) and SE(PHC) after conducting site visit. |
Thiruvananthapuram Project AE3 |
|
09 Aug 2021 |
Acquisition process is in progress . 11(1) notification issued. 19(1) notification awaited. Land Survey Completed and valuation in progress. Enquired at Land Aquisition wing regarding Advance possession and they conveyed that as Per section 40 of the LARR act Advanced posession clause can be revoked only in case of Natural disaster etc Out of Five revenue land proposals sent to Land revenue cmmisonerate two proposal have been returned to Collectorate LAnd transfer wing asking clarifications regarding an encroachment case for Land at Nellikunnu (Nedumparambu) and in case of WTP Land whether land have been allocated to exisitng Anganwadi and Library in same Survey number. The estimate of the WTP has been submitted after incorporation changes suggested by SE(SR) and SE(PHC) after conducting site visit. |
Thiruvananthapuram Project AE3 |
|