13 Dec 2022 KIIFB package approval pending due to non obtaining of KRFB road cutting permission. Work of WTP not started in revenue land, due to delay in permission from Panchayath for demolishing of Anganwadi at site. OHSR land at Nellikunnu, near Nedumparambu HSS not handed over by Education department. Alternate land for OHSR at Paramukku not handed over by revenue. Thiruvananthapuram Project AE3
18 Nov 2022 KRFB road cutting permission pending for 2 roads - Vamanapuram Chittar road and Kilimanoor-Alamcode road. KIIFB package approval pending in PFMS for the work. OHSR site at Paramukku cannot be handed over due to functioning of nearby quarry and access blocked. OHSR site at Nellikkunnu yet to hand over by Education department. Process ongoing in office of Deputy Director of Education. Thiruvananthapuram Project AE3
07 May 2022 Dy.Collector (LA) has issued a letter demanding additional amount of Rs.35,81,193/- for the acquisition of private lands. The same has been requested to KIIFB. Thiruvananthapuram Project AE3
28 Apr 2022 The new land near Nedumparambu School - Nagaroor panchayath council approved and requested Permission for taking over the land from Education Dept. through Hon. MLA, Attingal. Transfer of remaining revenue lands under process. Thiruvananthapuram Project AE3
24 Apr 2022 Extra amount of 35Lakhs demanded by Dy.Collector (LA), Tvpm for acquisition of 2 nos of private lands. Revenue lands transfer process ongoing in Revenue(U), Govt. Secretariate,Tvpm Thiruvananthapuram Project AE3
19 Apr 2022 KRFB sanction and demand note given for 1 no. of crossing. Remaining stretches to be given. Revenue land transfer process ongoing in Revenue (U) dept. Govt. Secretariate. Private land acquisition process in final stage in Collectorate. Thiruvananthapuram Project AE3
02 Apr 2022 On meeting with KRFB, it was informed that the Kilimanoor-Alamcode road is in DLP and consent to be taken from KIIFB for giving permission for road cutting. The case of VC road, permission will be given, once the work is rearranged and new contractor takes the work of the road. Thiruvananthapuram Project AE3
29 Mar 2022 On meeting with KRFB, it was informed that the Kilimanoor-Alamcode road is in DLP and consent to be taken from KIIFB for giving permission for road cutting. The case of VC road, permission will be given, once the work is rearranged and new contractor takes the work of the road. Thiruvananthapuram Project AE3
27 Mar 2022 Revenue land acquisition file sent to Land Revenue Commissionerate for further processing as per the information received from Revenue(U) section U3/242/2021 dt. 08.03.2022. But processing yet to start at LRC,Tvpm. Private land acquisition process in final stage. Road restoration estimates yet to receive from KRFB. Thiruvananthapuram Project AE3
25 Mar 2022 Revenue land acquisition file sent to Land Revenue Commissionerate for further processing as per the information received from Revenue(U) section U3/242/2021 dt. 08.03.2022. But processing yet to start at LRC,Tvpm. Private land acquisition process in final stage. Road restoration estimates yet to receive from KRFB. Thiruvananthapuram Project AE3