- Home
- KIIFB : CWSS to Pulimath,Nagaroor and Ka...
KIIFB : CWSS to Pulimath,Nagaroor and Karavaram Panchayaths Phase I
Project |
KIIFB : CWSS to Pulimath,Nagaroor and Karavaram Panchayaths Phase I |
Project Code |
TVMKIIFB0219618 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
CWSS to Pulimath, Nagaroor and KAravaram Panchayaths Phase I includes Production components only
Intake well of 9m dia at Anakudy 18MLD WTP at Kutiimoodu
OHSR 2.8 Lakh Litres Kadalkanipara OHSR 15.3 Lakh Litres Nagaroor Paramukku OHSR 14 Lakh Litres Nellikunnu, Nedumparambu
Sump 0.65 Lakh Litres Pavalla
OHSR 5.2 Lakh Litres Vandithadam Karavaram
RW Pumping Main-500mm DI – 4900 m Anakudy Well to WTP
CW Pumping Main 150mm DI – 1775 m WTP to Kadalkanipara OHSR
200mm DI – 1751 m Pavalla Sump to Vandithadam OHSR
Transmission Mains
450mm DI –10930 m WTP – Nagaroor Jn
400mm DI - 1782 m Nagaroor Jn – Paramukku OHSR
400mm DI – 3478 m Nagaroor Jn – Nellikunnu OHSR
200mm DI – 4759 m Nedumparambu to Pavalla Sump |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
818100000
|
AS Number |
APR-4/401/2018/KIIFB |
TS Amount (Rs) |
707816000 |
TS Number |
TS/2021-2022/2020/1628,3798,3805,8281,11901,, TS/2021-2022/2021/40770, 40771, 40775, 40778,41366 |
Total Bill Submitted (Rs) |
325717006 |
Total Bill Paid (Rs) |
325717006 |
Population Benefitted |
89465 |
Capacity in MLD |
18.00 |
Actual Project Completion Date |
30 May 2024 |
Coverage |
Pulimath Nagaroor and Karavaram Panchayaths. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB: CWSS to Pulimath, Nagaroor & Karavaram Panchayaths - Phase-I, (Package -1,2,3,4,5,6 and 7) - Construction of 9mWell cum pump house, Raw water pumping main, 18 MLD WTP and allied items, transformer at well site, raw water pump sets, OHSRs, Sump, Road restoration and Clear water pumping main |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Feb 2024 |
All the works of the scheme are progressing. Anganwadi land for Pulimath panchayath in the scheme not given by Revenue department. Revised AS submitted to KIIFB for PWD road cutting permission and other items. Bridge crossing permission for transmission line laying denied by PWD Bridges. |
Thiruvananthapuram Project AE3 |
|
03 Sep 2023 |
The access road formation is alternate land of 15.3 LL OHSR at Paramukku is ongoing. KRFB road cutting sanction denied by KRFB for Kilimanoor-Alamcode road, and permission will be given after handing over to PWD Roads Division, Tvpm after DLP period expiring on 30-09-2023. |
Thiruvananthapuram Project AE3 |
|
24 Jul 2023 |
The alternate OHSR land - 15.3LL OHSR at Paramukku - access road formation by Nagaroor Grama Panchayath is pending. KRFB estimate for permission in Kilimanoor-Alamcode road is pending from KRFB. |
Thiruvananthapuram Project AE3 |
|
28 May 2023 |
KRFB estimates for Kilimanoor-Alamcode road not yet given. The access pathway to 15.3LL OHSR new land near Thannikonam not yet done by Nagaroor panchayath authorities. |
Thiruvananthapuram Project AE3 |
|
15 Apr 2023 |
TS approval from KIIFB pending due to which 1st part bill for the work not able to upload in KIIFB PFMS portal. Several reminders with required documents for TS and package approval submitted to KIIFB for approval. Road formation to 15.3 LL OHSR- new site at Thannikonam in Nagaroor panchayath not yet finalized by panchayath authorities. |
Thiruvananthapuram Project AE3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
07/02/2019 |
Scheduled date of Completion of the Project |
31 Mar 2024 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
07 Feb 2019 |
TS Date |
25 Apr 2022 |