Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Mar 2022 |
Private land acquisition in final stage. Revenue land transfer process ongoing in Land REvenue COmmissionerate. |
Thiruvananthapuram Project AE3 |
|
16 Mar 2022 |
Private land (2 nos) acquisition process in final stage at Collectorate, Tvpm. Valuation of trees done as part of acquisition. Notice issued to owners. Revenue land transfer process file pending at Govt. Secretariate, Revenue(U) dept. Road restoration estimates pending from KSTP and KRFB. |
Thiruvananthapuram Project AE3 |
|
11 Mar 2022 |
Land acquisition of 2 private lands in progress. Notice issued by Collectorate to parties. Tree valuation report recieved except from Social Forestry dept. PRICE estimates pending for inclusion in estimate for TS from KRFB and KSTP. |
Thiruvananthapuram Project AE3 |
|
08 Mar 2022 |
Land acquisition of 2 private lands in progress. Notice issued by Collectorate to parties. Tree valuation report recieved except from Social Forestry dept. PRICE estimates pending for inclusion in estimate for TS from KRFB and KSTP. |
Thiruvananthapuram Project AE3 |
|
06 Mar 2022 |
Land acquisition of 2 private lands in progress. Notice issued by Collectorate to parties. Tree valuation report recieved except from Social Forestry dept. PRICE estimates pending for inclusion in estimate for TS from KRFB and KSTP. |
Thiruvananthapuram Project AE3 |
|
02 Mar 2022 |
Land acquisition process ongoing for Pvt lands and revenue land transfer. For the 4 revenue lands, the file with Under secretary, Revenue (U) dept. Govt. Secretariate. Tree value fixing from Social Forestry department done of 2 pvt. lands, Report yet to be received at Collectorate. Estimates in PRICE pending from KRFB and KSTP for including in Package-6 for TS. |
Thiruvananthapuram Project AE3 |
|
27 Feb 2022 |
Land acquisition process ongoing for Pvt lands and revenue land transfer. For the 4 revenue lands, the file with Under secretary, Revenue (U) dept. Govt. Secretariate. Tree value fixing from Social Forestry department done of 2 pvt. lands, Report yet to be received at Collectorate. Estimates in PRICE pending from KRFB and KSTP for including in Package-6 for TS. |
Thiruvananthapuram Project AE3 |
|
25 Feb 2022 |
Land acquisition process ongoing for Pvt lands and revenue land transfer. For the 4 revenue lands, the file with Under secretary, Revenue (U) dept. Govt. Secretariate. Tree value fixing from Social Forestry department done of 2 pvt. lands, Report yet to be received at Collectorate. Estimates in PRICE pending from KRFB and KSTP for including in Package-6 for TS. |
Thiruvananthapuram Project AE3 |
|
21 Feb 2022 |
Land acquisition process ongoing for Pvt lands and revenue land transfer. For the 4 revenue lands, the file with Under secretary, Revenue (U) dept. Govt. Secretariate. Tree value fixing from Social Forestry department pending for acquisition of 2 pvt. lands. Estimates in PRICE pending from KRFB and KSTP for including in Package-6 for TS. |
Thiruvananthapuram Project AE3 |
|
19 Feb 2022 |
Land acquisition process ongoing for Private and revenue lands. For private lands, tree value fixing is in final stage before acquisition of lands. Revenue land transfer is in final stage. Estimates from KRFB and KSTP pending for including in TS of road restoration package. |
Thiruvananthapuram Project AE3 |
|