Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Feb 2022 |
Land acquisition process ongoing for revenue and private lands. Estimates of road restoration pending from KSTP and KRFB. |
Thiruvananthapuram Project AE3 |
|
12 Feb 2022 |
Land acquisition process ongoing. Road restoration estimates pending from KRFB and KSTP for including in Package-6. Joint inspection completed for KSTP crossing at Karette junction. |
Thiruvananthapuram Project AE3 |
|
09 Feb 2022 |
Estimates not received from KRFB-PMU. TS approval of estimates of road restoration package pending. Land acquisition process ongoing. Tendering process started for Packages - 1,2 and 7. |
Thiruvananthapuram Project AE3 |
|
08 Feb 2022 |
Estimates not received from KRFB-PMU. TS approval of estimates of road restoration package pending. Land acquisition process ongoing |
Thiruvananthapuram Project AE3 |
|
06 Feb 2022 |
Estimates not received from KRFB-PMU. TS approval of estimates of road restoration package pending. Land acquisition process ongoing. |
Thiruvananthapuram Project AE3 |
|
03 Feb 2022 |
TS approved for all components except road restoration package.EE, KRFB-PMU, Tvpm informed that road restoration estimates for 2 stretches coming under KRFB can be given only after getting consent from funding agency. TS pending for road restoration package due to want of estimates from KRFB. Land acquisition process ongoing. The OHSR land (14LL) at Nellikkunnu, for which OS filed by opponent, judgement in favour of opponent came as informed by Thahazildar. |
Thiruvananthapuram Proj Dn AEE 2 |
|
01 Feb 2022 |
EE, KRFB-PMU, Tvpm informed that road restoration estimates for 2 stretches coming under KRFB can be given only after getting consent from funding agency. TS pending for road restoration package due to want of estimates from KRFB. Land acquisition process ongoing. The OHSR land (14LL) at Nellikkunnu, for which OS filed by opponent, judgement in favour of opponent came as informed by Thahazildar. TS approved for all production components except road restoration package. |
Thiruvananthapuram Project AE3 |
|
01 Feb 2022 |
EE, KRFB-PMU, Tvpm informed that road restoration estimates for 2 stretches coming under KRFB can be given only after getting consent from funding agency. TS pending due to want of estimates from KRFB. Land acquisition process ongoing. |
Thiruvananthapuram Project AE3 |
|
28 Jan 2022 |
Road restoration estimates from KRFB, Tvpm pending of Paramukku-Nagaroor stretch (in Kilimanoor - Alamcode road) and Vamanapuram-Chittar road. TS pending due to this. Land acquisition process ongoing for both revenue lands and private lands. |
Thiruvananthapuram Project AE3 |
|
24 Jan 2022 |
PWD attested estimates from PWD Roads Division obtained for one stretch. Pending for another stretch from Roads Division, Tvpm and from KRFB. |
Thiruvananthapuram Project AE3 |
|