Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Jan 2022 |
TS approved for 6 packages except road restoration package, for want of attested copies of PRICE estimate from PWD. Tress value fixing for Detailed Valuation Report preparation ongoing. Revenue land transfer ongoing. |
Thiruvananthapuram Project AE3 |
|
18 Jan 2022 |
Trees value fixing process ongoing by concerned depts. Revenue land transfer under process. |
Thiruvananthapuram Project AE3 |
|
12 Jan 2022 |
Land acquisition process ongoing. Value of trees at 2 pvt lands need to assessed by concerned depts. 4 packages - estimates TS approved. |
Thiruvananthapuram Project AE3 |
|
10 Jan 2022 |
Land acquisition process ongoing. Estimates under scrutiny for TS approval. |
Thiruvananthapuram Project AE3 |
|
09 Jan 2022 |
Reg. acquisition of two private lands, letter for deciding rate for tree cutting received from Dy.Collector (L&A), after BVR approval and for preparation of Detailed Valuation Report. Revenue land transfer process ongoing at Secretariate, Thiruvananthapuram. |
Thiruvananthapuram Project AE3 |
|
06 Jan 2022 |
BVR report signed by Dist. Collector, Thiruvananthapuram for the acquisition of two private lands at Anakudy and Vandithadam received. Revenue land transfer process ongoing at Secretariate, Tvpm. |
Thiruvananthapuram Project AE3 |
|
02 Jan 2022 |
BVR report signed by Dist. Collector, Thiruvananthapuram for the acquisition of two private lands at Anakudy and Vandithadam received. Revenue land transfer process ongoing at Secretariate, Tvpm. |
Thiruvananthapuram Project AE3 |
|
31 Dec 2021 |
BVR report signed by Dist. Collector, Thiruvananthapuram for the acquisition of two private lands at Anakudy and Vandithadam received. Revenue land transfer process ongoing at Secretariate, Tvpm. |
Thiruvananthapuram Project AE3 |
|
30 Dec 2021 |
Copy of BVR received officially. Revenue land transfer process ongoing at Secretariat, Revenue (U) dept. |
Thiruvananthapuram Project AE3 |
|
29 Dec 2021 |
BVR signed by Dist. Collector, Thiruvananthapuram. DVR will be prepared after this, on getting required clearances. Revenue land transfer file with Addl. Secretary at Revenue(U) department. TS estimates under scrutiny at CE office. |
Thiruvananthapuram Project AE3 |
|