Status Date |
Overall Project Status |
Project Officer |
Contact |
08 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|
07 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|
06 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|
05 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|
04 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|
03 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|
02 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|
01 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|
31 Mar 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 49568.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|
30 Mar 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 49568.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. |
Nattika Project Dn AE 2 |
|