Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Mar 2024 Package 1-pipe laid: 732 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
08 Mar 2024 Package 1-pipe laid: 732 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
07 Mar 2024 Package 1-pipe laid: 732 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
06 Mar 2024 Package 1-pipe laid: 732 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
05 Mar 2024 Package 1-pipe laid: 732 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
04 Mar 2024 Package 1-pipe laid: 630 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
03 Mar 2024 Package 1-pipe laid: 630 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
02 Mar 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
01 Mar 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
29 Feb 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2