Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4, P2D3 and P2D4 completed. Boring of P1C3 pile ongoing. Nattika Project Dn AE 2
26 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completedBoring of pile P2D3 pile is completed. Hardrock found at 35.5m and it is drilled to .6m and the total length of 36.1m is achieved. Reinforcement cage inserted . Concreting of P2D3 pile completed at 8pm with third party inspection. Nattika Project Dn AE 2
25 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.Boring of P2D3 pile ongoing. Nattika Project Dn AE 2
24 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.Boring of P2D3 pile ongoing. Nattika Project Dn AE 2
23 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
22 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
21 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
20 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
19 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
18 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2