Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
18 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
17 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
16 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
15 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
14 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
13 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
12 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
11 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
10 Feb 2024 | Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 |