Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Boring for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|
27 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Boring for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|
26 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Boring for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|
25 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Boring for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|
24 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Boring for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|
23 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|
22 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|
21 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|
20 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|
19 Apr 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation ongoing. |
Nattika Project Dn AE 2 |
|