Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 & P2A5 completed.Boring of pile foundation P1B5 ongoing. Nattika Project Dn AE 2
17 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 & P2A7 completed.Boring and Concreting of pile foundation P2A5 completed. Nattika Project Dn AE 2
16 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 & P2A7 completed. Nattika Project Dn AE 2
15 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 & P2D7 completed.Boring of pile foundation P2A7 ongoing. Nattika Project Dn AE 2
14 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 & P2D7 completed. Nattika Project Dn AE 2
13 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 & P2D7 completed. Nattika Project Dn AE 2
12 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7 & P1B6 completed.Boring of pile foundation P2D7 ongoing Nattika Project Dn AE 2
11 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7 & P1B6 completed.Boring of pile foundation P2D7 ongoing Nattika Project Dn AE 2
10 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7 & P1B6 completed. Nattika Project Dn AE 2
09 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 , P2D2 &P2B1 completed.Boring of pile foundation P1C2 ongoing and P2A1 boring started. Nattika Project Dn AE 2