Status Date Overall Project Status Project Officer Contact
28 Feb 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
27 Feb 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
26 Feb 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
25 Feb 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
24 Feb 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
23 Feb 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
22 Feb 2024 Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
21 Feb 2024 Package 1-pipe laid: 450 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
20 Feb 2024 Package 1-pipe laid: 396 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
19 Feb 2024 Package 1-pipe laid: 120m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2