Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Feb 2024 | Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
27 Feb 2024 | Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
26 Feb 2024 | Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
25 Feb 2024 | Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
24 Feb 2024 | Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
23 Feb 2024 | Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
22 Feb 2024 | Package 1-pipe laid: 552 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
21 Feb 2024 | Package 1-pipe laid: 450 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
20 Feb 2024 | Package 1-pipe laid: 396 m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 | |
19 Feb 2024 | Package 1-pipe laid: 120m DI / 10937.5m,Cumulative pipe supplied 30920.5/50120m. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. | Nattika Project Dn AE 2 |