29 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 45484.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out and reinforcement work for Pile foundation on going. | Nattika Project Dn AE 2 | |
28 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 40684.5.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out for Pile foundation on going. | Nattika Project Dn AE 2 | |
27 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 40684.5.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out for Pile foundation on going. | Nattika Project Dn AE 2 | |
26 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 38920.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out for Pile foundation on going. | Nattika Project Dn AE 2 | |
25 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 32520.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out for Pile foundation on going. | Nattika Project Dn AE 2 | |
24 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 32520.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out for Pile foundation on going. | Nattika Project Dn AE 2 | |
23 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 32520.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved and Setting out for Pile foundation on going. | Nattika Project Dn AE 2 | |
22 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 32520.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed and Design approved | Nattika Project Dn AE 2 | |
21 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 32520.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed and Design approved | Nattika Project Dn AE 2 | |
20 Mar 2024 | Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 32520.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed and Design approved | Nattika Project Dn AE 2 |