Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 & P2D2 completed.concreting of pile foundation P2B1 completed. Nattika Project Dn AE 2
07 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 & P2D2 completed.Boring of pile foundation P2B1 completed. Nattika Project Dn AE 2
06 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 & P2D2 completed.Boring of pile foundation P2B1 discontinued due to site conditions. Nattika Project Dn AE 2
05 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 & P2D2 completed.Boring of pile foundation P2B1 discontinued due to site conditions. Nattika Project Dn AE 2
04 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 & P2D2 completed.Boring of pile foundation P2B1 discontinued due to site conditions. Nattika Project Dn AE 2
03 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 & P2D2 completed.Boring of pile foundation P2B1 discontinued due to site conditions. Nattika Project Dn AE 2
02 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 & P2D2 completed.Boring of pile foundation P2B1 discontinued due to site conditions. Nattika Project Dn AE 2
01 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 & P2D2 completed.Boring of pile foundation P2B1 ongoing. Nattika Project Dn AE 2
30 Apr 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2C1 & P2D2 completed. Nattika Project Dn AE 2
29 Apr 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Boring for pile foundation ongoing. Nattika Project Dn AE 2