Status Date Overall Project Status Project Officer Contact
09 Feb 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
08 Feb 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed.Design submitted to WASCON for approval. Nattika Project Dn AE 2
07 Feb 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. Nattika Project Dn AE 2
06 Feb 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. Nattika Project Dn AE 2
05 Feb 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. Nattika Project Dn AE 2
04 Feb 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. Nattika Project Dn AE 2
03 Feb 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. Nattika Project Dn AE 2
02 Feb 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. Nattika Project Dn AE 2
01 Feb 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. Nattika Project Dn AE 2
31 Jan 2024 Package 1- PVC pipe -20010 m supplied, DI pipe- 13045.5m supplied. Package 2- Bench mark fixing and initial level marking at site completed, OHSR Tank site clearance work completed. Nattika Project Dn AE 2