Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. |
Nattika Project Dn AE 2 |
|
16 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. |
Nattika Project Dn AE 2 |
|
15 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. |
Nattika Project Dn AE 2 |
|
14 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. |
Nattika Project Dn AE 2 |
|
13 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. |
Nattika Project Dn AE 2 |
|
12 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. |
Nattika Project Dn AE 2 |
|
11 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. |
Nattika Project Dn AE 2 |
|
10 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.Cleaning ongoing. |
Nattika Project Dn AE 2 |
|
09 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed. |
Nattika Project Dn AE 2 |
|
08 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed. |
Nattika Project Dn AE 2 |
|