Status Date Overall Project Status Project Officer Contact
17 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
16 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
15 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
14 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
13 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
12 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
11 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.site clearance ongoing. Nattika Project Dn AE 2
10 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed.Cleaning ongoing. Nattika Project Dn AE 2
09 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed. Nattika Project Dn AE 2
08 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 , P1C4 and P2D4 completed. Nattika Project Dn AE 2