Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 and P1C4 completed.concreting of pile foundation P2D4 completed. |
Nattika Project Dn AE 2 |
|
06 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 and P1C4 completed.Boring of pile foundation P2D4 ongoing. |
Nattika Project Dn AE 2 |
|
05 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 and P1C4 completed.Boring of pile foundation P2D4 ongoing. |
Nattika Project Dn AE 2 |
|
04 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 and P1C4 completed. |
Nattika Project Dn AE 2 |
|
03 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed.Boring of pile foundation P1C4 ongoing . |
Nattika Project Dn AE 2 |
|
02 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed.Boring of pile foundation P1B4 ongoing . |
Nattika Project Dn AE 2 |
|
01 Jun 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed. |
Nattika Project Dn AE 2 |
|
31 May 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed. |
Nattika Project Dn AE 2 |
|
30 May 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed.Boring of pile foundation P1B4 ongoing. |
Nattika Project Dn AE 2 |
|
29 May 2024 |
Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 & P1C5 completed.Boring of pile foundation P1B4 started. |
Nattika Project Dn AE 2 |
|