Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 and P1C4 completed.concreting of pile foundation P2D4 completed. Nattika Project Dn AE 2
06 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 and P1C4 completed.Boring of pile foundation P2D4 ongoing. Nattika Project Dn AE 2
05 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 and P1C4 completed.Boring of pile foundation P2D4 ongoing. Nattika Project Dn AE 2
04 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5, P2D5 and P1C4 completed. Nattika Project Dn AE 2
03 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed.Boring of pile foundation P1C4 ongoing . Nattika Project Dn AE 2
02 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed.Boring of pile foundation P1B4 ongoing . Nattika Project Dn AE 2
01 Jun 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed. Nattika Project Dn AE 2
31 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed. Nattika Project Dn AE 2
30 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 ,P1C5 & P2D5 completed.Boring of pile foundation P1B4 ongoing. Nattika Project Dn AE 2
29 May 2024 Package 1-pipe laid: 732 m DI / 10937.5m, Cumulative pipe supplied 50997.5/50120m. Package 2- OHSR Tank site Bench mark fixing and initial level marking at site completed ,Design approved ,sub soil investigation for pile foundation completed.Concreting of pile foundation P2A6 , P2B7 ,P2C7, P1B6 , P2D7 , P2A7 , P2A5 ,P1B5,P1C6 & P2D6 & P1C5 completed.Boring of pile foundation P1B4 started. Nattika Project Dn AE 2