Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Nov 2023 In package 1, 93% - Raw water pumphouse, Raw water pumping main, and Booster station are in Finishing stage. 23 MLD WTP, 12 LL OHSR, All gravity and pumping mains are completed. In package 2, Work short closed. in package 3a, Tender approval obtained from govt. and work awarded on 31/05/2023. Design of pump set are completed and pump set order is placed by the contracter. In package 3b, Work Awarded. In package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Direction was given by Secretary to Government, Water Resources (WS-C) Department to CE (I&A) to prepare a submite DPR of the subject work for Administrative Saction on 19/08/2023. In packge 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
12 Sep 2023 In package 1, 92% - Pump house and substation building works are completed. Leading chanel work 70% completed. Row water pumping main completed. Anchor blocks 90% completed. Pressure testing of Raw water pumping main in MS portion to be done. Booster station work completed. Water tightening test to be done. WTP is completed. 12 LL OHSR in AMU campus is completed. Clear water pumping main/ Gravity main are completed. KSEB power line extension is required for the commissioning of the scheme. KIIFB asked for resubmit the demand (of 6.25 cr recieved from KSEB) with out supervision charge. The same is not obtained from KSEB yet. Package 2, 93% - All works are completed except the replacement of old AC pipe with DI for a length of 4.5 KM along NH 966, as the road cutting permission was not obtained from the NHAI. so Work short closed. Package 3A, Tender approval obtained from govt. and work awarded on 31/05/2023. Design of pump set are completed and pump set order is placed by the contracter. Package 3B, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. TS approved, Under Tendering Procedure. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
01 Aug 2023 In package 1, 91% - Raw water pumping main 695 m (600mm DI) laying done. Laying MS row water pumping main on going and anchor block work ongoing. RWPM Air Valve Fixing Completed. Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (Handrail and Paiting works completed) Well cum Pump house (Plastering work and fabrication works for windows and doors completed. Painting Work completed. (Booster cum pump house) plastering in progress, pumphouse flooring PCC work completed. Leading Channel work in progress. Package 2, 93% - Work short closed. Package 3A, Tender approval obtained (No : 27/2023/WRD DTD. 24/04/2023). Work awarded and site handed over. Package 3B, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. TS approved, Re-Tendered. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
20 Jul 2023 In package 1, 91% - Raw water pumping main 695 m (600mm DI) laying done. Laying MS row water pumping main on going and anchor block work ongoing. RWPM Air Valve Fixing Completed. Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (Handrail and Paiting works completed) Well cum Pump house (Plastering work and fabrication works for windows and doors completed. Painting Work completed. (Booster cum pump house) plastering in progress, pumphouse flooring PCC work completed. Leading Channel work in progress. Package 2, 93% - Work short closed. Package 3A, Tender approval obtained (No : 27/2023/WRD DTD. 24/04/2023). Work awarded and site handed over. Package 3B, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. TS approved, Re-Tendered. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
30 Jun 2023 In package 1, 90% - Raw water pumping main 695 m (600mm DI) laying done. Laying MS row water pumping main on going. RWPM Air Valve Fixing Completed. Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (Handrail works and Paiting work progress.) Well cum Pump house (Plastering work and fabrication works for windows and doors under progress. Painting Work progress. (Booster cum pump house) plastering in progress, pumphouse flooring PCC work in progress. Leading Channel work in progress. Package 2, Work Short closed. Package 3A, Tender approval obtained (No : 27/2023/WRD DTD. 24/04/2023). Work awarded and site handed over. Package 3B, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. TS approved, Re-Tendered. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
01 Jun 2023 In Package 1, 89%- Raw water pumping main 695 m (600mm DI) laying done. Laying MS row water pumping main on going. RWPM Air Valve Fixing Completed. Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (Handrail works and Paiting work progress.) Well cum Pump house (Plastering work and fabrication works for windows and doors under progress. Painting Work progress. (Booster cum pump house) plastering in progress, pumphouse flooring PCC work in progress. Leading Channel work in progress. Package 2, Work Closed. Package 3A, Tender approval obtained (No : 27/2023/WRD DTD. 24/04/2023). Package 3B, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. TS approved, Re-Tendered. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
03 May 2023 In package 1, 88%- In package 1, 96%- 8400 m of 350mm DI K9 CWPM laid in a total of of 8400m from ongoing WTP site to ongoing 23 LL OHSR for Edayur GP at Safa and 2770 m of 600 mm DI K9 RWPM laid in a total of 2770m. At Safa OHSR Painting work completed. At WTP Compound wall work in progress. sub station building (compound wall work in progress and Painting Work under progress). 60 HP Pumpsets 2 Nos Installed. Ramp work (painting work in progress) Pump set errected . 350 DI pipeline fabrication work in inter connection gap under progress. Sump plastering completed. Package 2, 89%- 90005 M PVC pipes laid. Balance 61.4 KM PVC pipes of various sizes received and laying work ongoing. 400 DI 625 m, 350 DI 3151 m, 300 DI 1614 m, 200 DI 615 m and 250 DI 3180 m laid. Anchor block and valve chamber work in progress. Package 3A, 93%- Construction of Transformer Room finishing work in progress. (Pump set errection progress. Transformer supply and errection completed). For power connection, line extension (Arial Bunched Cable(ABC)) and post errection works of KSEB Under progress. Package 2, Work short closed. Package 3, Tender approval to be obtained on 05/09/2022, send to govt for tender approval. New the file at Finance Department. Package 3B, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. TS approved, Re-Tendered. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
01 Apr 2023 In package 1, 87%- Raw water pumping main 695 m (600mm DI) laying done. Laying MS row water pumping main on going. RWPM Air Valve Fixing Completed. Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (Handrail works and Paiting work progress.) Well cum Pump house (Plastering work and fabrication works for windows and doors under progress. Painting Work progress). (Booster cum pump house) plastering in progress. Leading Channel work in progress. Package 2, Work Short closed. Package 3A, Tender approval to be obtained on 05/09/2022, send to govt for tender approval. New the file at Finance Department. Package 3B, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. TS approved, Tender opening on 18/03/2023. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
14 Mar 2023 In package 1, 86%- Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (Handrail works and Paiting work progress.) Well cum Pump house (Plastering work and fabrication works for windows and doors under progress. Painting Work progress.) Handarail works completed. (Booster cum pump house) plastering in progress. Pump house roof slab concrete work completed. Laying MS row water pumping main on going. Leading Channel work in progress. In package 2, 93%- All works are completed except the replacement of old AC pipe with DI for a length of 4.5 KM along NH 966. As the road cutting permission was not obtained from the NHAI, the work is short closed. In package3A, Tender approval to be obtained on 05/09/2022, send to govt for tender approval. New the file at Finance Department. In package 3B, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. TS approved, Tender opening on 18/03/2023. In package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. In package 5, Got TS. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
28 Feb 2023 In package 1, 86%- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction Completed. Compound wall construction and Mechanical Works completed. Painting work completed. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (Handrail works and Paiting work progress.) Well cum Pump house (Plastering work and fabrication works for windows and doors under progress. Painting Work progress.) Road restorarion GSB wet mix filling work Completed in PWD Roads. (Booster cum pump house) plastering in progress. Pump house roof slab concrete work completed. Laying MS row water pumping main on going. Ramp work (Handrail work completed.). In package 2, 93%- 33611 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38985 m DI pipes. Parallel rider main of 90 mm PVC pipes for the length of 34254 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. Valve chamber work in progress. MS gsp filling work ongoing. Line charging under progress. In package 3A- Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. In package 3B- Tender approval to be obtained. In package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. In package 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3