| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Jun 2021 | 28% of package 1 and 34% of package2 completed Revised estimate got approved to facilitate the changes in the raw water pipe line alignment and location of well cum pump house in package 1 | Malappuram Project Dn AE3 | |
| 01 Jun 2021 | 28% of Package 1 and 34 % of Package 2 Completed. | Malappuram Project Dn AE3 | |
| 26 May 2021 | 28% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
| 05 May 2021 | 26% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
| 26 Apr 2021 | 26% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
| 19 Apr 2021 | 26% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
| 13 Apr 2021 | 25% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
| 12 Apr 2021 | 25% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
| 09 Apr 2021 | 24% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
| 08 Apr 2021 | 24% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 |