Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Aug 2022 In package 1, 75 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Finishing work in progress). Compound wall construction and Mechanical Works in progress. Painting work in progress. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work in progress. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8010 m (450 mm DI) laying done. Pump house grantry girder beam work and column work completed. In package 2, 84 % - 32790 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 32790 m are also laid. 7000 m of 250 mm DI piping for clear water gravity main laid. Malappuram Project Dn AE3
24 Aug 2022 In package 1, 73 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Finishing work in progress). Compound wall construction and Mechanical Works in progress. Painting work in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8010 m (450 mm DI) laying done. Pump house grantry girder beam work completed and column work in progress. In package 2, 79 % - 32680 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 32680 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. package 3- Selection notice issued, Agreement not executed Malappuram Project Dn AE3
20 Aug 2022 In package 1, 73 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Finishing work in progress). Compound wall construction and Mechanical Works in progress. Painting work in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8010 m (450 mm DI) laying done. Pump house grantry girder beam work completed and column work in progress. In package 2, 79 % - 32680 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 32680 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. Malappuram Project Dn AE3
12 Aug 2022 In package 1, 72 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 7980 m (450 mm DI) laying done. Pump house beam RCC work completed. In package 2, 32500 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 32500 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. Malappuram Project Dn AE3
25 Jul 2022 In package 1, 70 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 7980 m (450 mm DI) laying done. Pump house Brick work in progress. In package 2, 78 % - 32210 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 32210 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. Malappuram Project Dn AE3
11 Jul 2022 In package 1, 69 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 7730 m (450 mm DI) laying done. floor beam shuttering work of pump house in progress. In package 2, 77 % - 31968 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 31968 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under Tendering process. In package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready by May end. In package 5, Estimate TS Approved. Malappuram Project Dn AE3
10 Jun 2022 In package 1, 67 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 5840 m (450 mm DI) laying done. Well 8th lift steel and shuttering work in progress In package 2, 74 % - 30358 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 30358 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering work. Malappuram Project Dn AE3
27 May 2022 Delay of package 1 The work was temporary halted from 22/05/22 to 26/05/22 as the well was filled with water from the thootha river. Malappuram Project Dn AE3
27 May 2022 In package 1, 67 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 5730 m (450 mm DI) laying done. Well 6th lift RCC works completed. In package 2, 74 % - 30293 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 30293 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. Malappuram Project Dn AE3
11 May 2022 In package 1, 67 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 5350 m (450 mm DI) laying done. Well 4th lift shuttering and steel work in progress. In package 2, 74 % - 30173 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 30173 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. Malappuram Project Dn AE3