Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Apr 2022 |
In package 1, 66 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 5100 m (450 mm DI) laying done. Steel work of the well completed and well bottom rcc work started. In package 2, 73 % - 30018 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 30018 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. |
Malappuram Project Dn AE3 |
|
12 Apr 2022 |
In package 1, 65%- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 4980 m (450 mm DI) laying done. Well excavation work completed. In package 2, 73%- 29888 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29888 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, under tendering process. |
Malappuram Project Dn AE3 |
|
08 Apr 2022 |
In package 1, 64% - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 4950 m (450 mm DI) laying done. Well excavation work in progress. In package 2, 73% - 29838 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29838 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. |
Malappuram Project Dn AE3 |
|
01 Apr 2022 |
In package 1, 64 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 4850 m (450 mm DI) laying done. Well excavation work in progress. In package 2, 73 %- 29728 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29728 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. |
Malappuram Project Dn AE3 |
|
22 Mar 2022 |
IN package 1, 63% - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 4730 m (450 mm DI) laying done. Well excavation work in progress. In package 2, 72% - 29598 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29598 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering Process. |
Malappuram Project Dn AE3 |
|
18 Mar 2022 |
The delay in start of the Well and RWPM and substation works is due to change in the location of the weir and associated change in pumping main alignment. The well and pumping main work is ongoing now. For package -2 mainly 4.5KM pipe line along NH-966 in Perinthalamanna is pending for want of permission from NHAI . For Package-3 covering electromechanical works, work order was issued, however contractor did not execute agreement. Retendering is to be done. |
Malappuram Project Dn AE3 |
|
15 Mar 2022 |
In package 1, 62%- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 4660 m (450 mm DI) laying done. Well excavation work in progress. In package 2, 72%- 29558 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29558 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under Tendering process. |
Malappuram Project Dn AE3 |
|
08 Mar 2022 |
In package 1, 62%- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 4630 m (450 mm DI) laying done. Well excavation work in progress. In package 2,. 72%- 29543 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29543 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3 , Under tendering process. |
Malappuram Project Dn AE3 |
|
28 Feb 2022 |
In package 1, 61%- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Roof slab concrete work completed). Compound wall construction and Mechanical Works in progress. filtermedia filling work under progress. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 4500m (450 mm DI) laying done. Well excavation work in progress. In package 2, 72%- 29522 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29522 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. In package 3, Under tendering process. |
Malappuram Project Dn AE3 |
|
28 Feb 2022 |
In package 2, 72%- 29522 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38695 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 29522 m are also laid. 4600 m of 250 mm DI piping for clear water gravity main laid. |
Malappuram Project Dn AE3 |
|