15 Feb 2023 In package 1, 86 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction Completed. Compound wall construction and Mechanical Works completed. Painting work completed. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building ( Handrail works in progress.) Well cum Pump house (Plastering work in progress and fabrication works for windows and doors under progress.) Road restorarion GSB wet mix filling work Completed in PWD Roads. (Booster cum pump house) Brick work completed and plastering in progress. Lintel with sunshade concrete work completed. Laying MS row water pumping main on going. Ramp work (Handrail work completed.) In package 2, 93 % - 33611 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38985 m DI pipes. Parallel rider main of 90 mm PVC pipes for the length of 34234 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. Valve chamber work in progress. MS gsp filling work ongoing. Line charging under progress. In package 3A, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Re-casted the estimate with new pipe rate in price 3 and submitted. In package 3B, Tender approval to be obtained. In package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. In package 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
25 Jan 2023 In package 1, Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction Completed. Compound wall construction and Mechanical Works completed. Painting work completed. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building ( Plastering work completed & fabrication works for windows and doors completed.) Well cum Pump house (Plastering work in progress and fabrication works for windows and doors under progress.) Road restorarion GSB wet mix filling work Completed in PWD Roads. (Booster cum pump house) Booster Cover slab Concrete work completed. pump house column work completed and brick work in progress. Plastering work started. Laying MS row water pumping main on going. Ramp work ( Slab concrete work completed.) In package 2, 93 % - 33611 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38945 m DI pipes. Parallel rider main of 90 mm PVC pipes for the length of 33124 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. Valve chamber work in progress. MS gsp filling work ongoing. Line charging under progress. In package 3A, Tender awarded in LMR rate. Contractor denied to executed the agreement. Tender cancelled. Recasted the estimate with new pipe rate in price 3 and submitted. In package 3B, Tender approval to be obtained. In package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. In package 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
23 Jan 2023 In package 1, 86 %- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction Completed. Compound wall construction and Mechanical Works completed. Painting work completed. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building ( Plastering work on going). Well cum Pump house (Plastering work in progress). Road restorarion GSB wet mix filling work Completed in PWD Roads. (Booster cum pump house) Cover slab shuttering work in progress.. Laying MS row water pumping main on going (840 m completed) . Ramp work ( Slab concrete work completed.) In package 2 - 33611 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38945 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 33124 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. Valve chamber work in progress. MS gsp filling work ongoing. Line charging under progress. package 3A, Tender cancelled. Package 3B, Tender approval to be obtained. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
05 Jan 2023 In package 1, 85 %- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction Completed. Compound wall construction and Mechanical Works completed. Painting work completed. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building ( Plastering work on going). Well cum Pump house (Plastering work in progress). Road restorarion GSB wet mix filling work Completed in PWD Roads. (Booster cum pump house) Cover slab shuttering work in progress.. Laying MS row water pumping main on going. Ramp work ( Slab concrete work completed.) In package 2 - 33611 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38945 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 33124 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. Valve chamber work in progress. MS gsp filling work ongoing. Line charging under progress. package 3A, Tender cancelled. Package 3B, Tender approval to be obtained. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
12 Dec 2022 In package 1, Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction Completed. Compound wall construction and Mechanical Works completed. Painting work completed. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building ( Brick work completed and plastering work on going). Well cum Pump house (Plastering work in progress). Road restorarion GSB wet mix filling work Completed in PWD Roads. (Booster cum pump house) side wall shuttering,steel & concreting work in progress. Laying MS row water pumping main on going. Ramp work ( Columns work completed. ).Package 2, 33611 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38945 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 33124 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. Valve chamber work in progress. MS gsp filling work ongoing. Line charging under progress. Package 3A, Tender cancelled. Package 3B, Tender approval to be obtained. Package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. Package 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
17 Nov 2022 In package 1, 81 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Finishing work in progress). Compound wall construction and Mechanical Works completed. Painting work in progress. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building ( Brick work in progress). Well cum Pump house (roof slab concrete work completed). Road restorarion GSB wet mix filling work Under progress in PWD Roads. (Booster cum pump house) base slab, column and side wall Steel work in progress. In package 2, 33611 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38945 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 33124 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. Road restoration GSB wet mix filling work Under progress in PWD Roads. Valve chamber work in progress. In package 3A, Tender cancelled. In package 3B, Tender approval to be obtained. In package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. In package 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
28 Oct 2022 In package 1, 81 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Finishing work in progress). Compound wall construction and Mechanical Works completed. Painting work in progress. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (Roof slab concrete work completed). Pump house (roof slab concrete work completed). Road restorarion GSB wet mix filling work Under progress in PWD Roads. In package 2, 33611 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38945 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 33124 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. Road restoration GSB wet mix filling work Under progress in PWD Roads. Malappuram Project Dn AE3
19 Oct 2022 In package 1, 80 % - Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Finishing work in progress). Compound wall construction and Mechanical Works completed. Painting work in progress. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (Roof beam shuttering And Steel work in progress). Pump house (roof slab concrete work completed) Booster earth levelling finished. In package 2, 33611 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38945 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 33124 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. In package 3a,3b,4 and 5 Non started. Malappuram Project Dn AE3
07 Oct 2022 In package 1, 79 %- Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Finishing work in progress). Compound wall construction and Mechanical Works completed. Painting work in progress. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Substation building (column work in progress). Pump house (roof slab shuttering and steel work in progress). In package 2, 93%- 37820 m of DI pipes for the distribution network are laid against the total scheduled quantity of 38945 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 32838.85 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. In package 3A, Work order issued. Agreement not executed. In package 3B, Tender approval to be obtained. In package 4, As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. In package 5, Got TS approval. Waiting for KIIFB package approval to start tendering process. Malappuram Project Dn AE3
28 Sep 2022 In package 1(78%)-Civil structure works of Aerator, Clariflocculator, flash mixer, Filter house ,Sump, back wash tank and clear water pump house completed.12LL OHSR construction under progress (Finishing work in progress). Compound wall construction and Mechanical Works in progress. Painting work in progress. filtermedia filling work completed. Panelboard for Clear water pumpset errected. Platesetler work completed. Raw water pumping main 695 m (600mm DI) laying done .Clear water pumping main work under progress. 1215 m (250 mm DI) piping done. 8030 m (450 mm DI) laying done. Pump house brick work completed . Substation building -Floor slab-(shuttering work in progress). well - roof beam shuttering and steel work in progress. In Package 2(91%)-36630m of DI pipes for the distribution network are laid against the total scheduled quantity of 38945 m DI pipes. Parallel rider main of 90 mm pvc pipes for the length of 32838.85 m are also laid. 6400.4 m of 250 mm DI piping for clear water gravity main laid. In package 3(a) - Work order issued. Agreement not executed. In package 3(b) -Work order issued. Agreement not executed. In package 4 -As per the joint meeting with CE irrigation with our CE,it is decided to deposit weir AS amount 2.9 crore rupees in the Irrigation project. Irrigation dept is progressing towards AS for their project. In joint meeting with CE irrigation and CR IDRB conducted on 11/04/2022, CE IDRB informed that the design will be ready soon. In package 5 -Estimate TS Approved. Malappuram Project Dn AE3