Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Apr 2021 | 24% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
05 Apr 2021 | 24% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
03 Apr 2021 | 24% of Package 1 and 33% of Package 2 Completed. | Malappuram Project Dn AE3 | |
31 Mar 2021 | 24% of package 1 and 33% of package 2 completed | Malappuram Project Dn AE3 | |
16 Mar 2021 | 23% of package 1 and 33% of package 2 are being done. Package 3 jobs are not yet startef | Malappuram Project Dn AE3 | |
10 Mar 2021 | overall progress for the project is 16 %. | Malappuram Project Dn AE3 | |
09 Mar 2021 | Construction of filterhouse , clariflocculator, sump etc under progress. 1630 m of 450 mm DI K9 clear water gravity main pipe laying done. Distribution network- 11372 m of DI K9 pipe has been laid for the distribution network in Perintalmanna municipality. Package 3 under preparation | Malappuram Project Dn AE3 | |
02 Feb 2021 | Construction of WTP components under progress. 1100 m out of 8600 m laying of clear water gravity main 450 mm DI pipe done. Laying of distribution network has been done for 9040 m out of 38695 m. | Malappuram Project Dn AE3 | |
26 Jan 2021 | WTP plant construction & clear water gravity main piping under progress - package 1 Replacement of old AC pipe with new DI K9 pipes under progress 8760m of DI pipes are laid out of 38695 m pipes communication under progress regarding the pipe laying thru NH(deposit amount is there in KIIFB approved DPR) Overall project progress is 12 percen | Malappuram Project Dn AE3 | |
26 Jan 2021 | WTP plant construction & clear water gravity main piping under progress - package 1 Replacement of old AC pipe with new DI K9 pipes under progress 8760m of DI pipes are laid out of 38695 m pipes communication under progress regarding the pipe laying thru NH(deposit amount is there in KIIFB approved DPR) Overall project progress is 12 percent | Malappuram Project Dn AE3 |