Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Oct 2021 52% of Package 1 and 51% of Package 2 completed Malappuram Project Dn AE3
22 Sep 2021 50% of Package 1 and 50% of package 2 completed Malappuram Project Dn AE3
09 Sep 2021 46% of Package 1 and 48% of package 2 completed Malappuram Project Dn AE3
27 Aug 2021 45% of Package 1 and 47 % of package 2 completed Malappuram Project Dn AE3
25 Aug 2021 32% of Package 1 and 41 % of package 2 completed Malappuram Project Dn AE3
30 Jul 2021 31% of Package 1 and 41 % of package 2 completed Malappuram Project Dn AE3
12 Jul 2021 30% of Package 1 and 36 % of package 2 completed Malappuram Project Dn AE3
01 Jul 2021 29% of Package 1 and 35 % of package 2 completed Malappuram Project Dn AE3
16 Jun 2021 29% of Package 1 and 35 % of package 2 completed Malappuram Project Dn AE3
14 Jun 2021 29% of Package 1 and 35 % of package 2 completed Malappuram Project Dn AE3