Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
10 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
09 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
08 Aug 2023 | Pkg A-35% & Pkg B-43% , Pkg D-1%-Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. | Thrissur PH Dn EE | |
07 Aug 2023 | Pkg A-35% & Pkg B-43% , Pkg D-1%-Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. | Thrissur PH Dn EE | |
05 Aug 2023 | Pkg A-35% & Pkg B-43% , Pkg D-1%-Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. | Thrissur PH Dn EE | |
04 Aug 2023 | Pkg A-35% & Pkg B-43% , Pkg D-1%-Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. | Thrissur PH Dn EE | |
03 Aug 2023 | Pkg A-35% & Pkg B-43% , Pkg D-1%-Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. | Thrissur PH Dn EE | |
02 Aug 2023 | Pkg A-35% & Pkg B-43% , Pkg D-1%-Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. | Thrissur PH Dn EE | |
01 Aug 2023 | Pkg A-35% & Pkg B-43% , Pkg D-1%-Pipe laying - work in progress Pkg C- 57 FHTCs given. Tagging on going-62%. | Thrissur PH Dn EE |