Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Sep 2023 | Pkg A-35% water connection work in progress & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work completed. -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
02 Sep 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work completed. -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
31 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work completed. -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
24 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work completed. -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
21 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work completed. -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
19 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work completed. -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
18 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work completed. -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
17 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work completed. -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
16 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE | |
14 Aug 2023 | Pkg A-35% & Pkg B-43% -Pipe laying - work in progress Pkg C- 57 FHTCs given. Pipe laying - work in progress -62%. Pkg D-1%-survey work in progress | Thrissur PH Dn EE |