Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Apr 2023 25 HTC outof 2218 connections completed.W8 Tagore road 110mm HDPE, W13 Nethajinagar road 90mm HDPE pipe laying Vadanappilly AE
24 Apr 2023 25 HTC outof 2218 connections completed. Edassery beach road 160mm HDPE, Tagore road, W8 Masjid road 90mm PVC, W12 Templeroad near Eranezhath 90mm PVC, W16 Ravinagar road 110mm HDPE pipe laying ongoing. Vadanappilly AE
19 Apr 2023 Second and part bill submitted,Aasad road-W7-63mm PVC , W1- Edassery Beach Road-160mm HDPE, W1-Vivekananda Road, W8-Puthanthodu Road-75mm PVC pipe laying Vadanappilly AE
17 Apr 2023 Second and part bill submitted, Vivekananda road W1 90 mm HDPE, W8 90mm HDPE Puthanthodu road, kunnathpally road W13, 90mm HDPE pipe laying. Vadanappilly AE
13 Apr 2023 Second and part bill submitted,Kunnathappally Road-w15-90mm Hdpe pipe laying,THAMBANKADAVU THRIVENI RD -WD2,160MM HDPE PIPE LAYING, Vadanappilly AE
10 Apr 2023 Puthanthode road, Ward 8, 90mm HDPE pipe laying,Andippura colony kunnathppally Road, Ward 15, 90mm HDPE pipe laying,140mm hdpe pipe laying at ward 1 tkm thambankadavu thriveni road, Vadanappilly AE
05 Apr 2023 Second and part bill submitted, Ward 15, 90mm HDPE pipe laying Ambalam Athmavu road, Ward 13, 90mm HDPE pipe laying at Ambalam Athmavu road Vadanappilly AE
03 Apr 2023 Second and part bill submitted, Ward 15, 90mm HDPE pipe laying Ambalam Athmavu road, Ward 13, 90mm HDPE pipe laying at Ambalam Athmavu road Vadanappilly AE
30 Mar 2023 Second and part bill submitted,Ward 1 pallikkadavu thambankadavu road 90mm hdpe,Ward 12, 160mm HDPE Badariyya masjid near thalikubgara temple road,Ward 15, nethaji nagar north, 90mm HDPE pipe laying Vadanappilly AE
27 Mar 2023 Second and part bill submitted Vadanappilly AE