Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 May 2023 | 1.7 % htc connections and 42.6 % pipe laying completed (32 HTC connections completed out of 2218 , 30144M pipe laying completed out of 70765M) | Vadanappilly AE | |
09 May 2023 | 1.7 % htc connections and 42.36 % pipe laying completed (32 HTC connections completed out of 2218 , 29976M pipe laying completed out of 70765M) | Vadanappilly AE | |
08 May 2023 | 1.7 % htc connections and 42.07 % pipe laying completed (32 HTC connections completed out of 2218 , 29770M pipe laying completed out of 70765M) 90mm HDPE pipe laying at Ideal nagar road,160mm HDPE pipe laying at Pallimukku Masjid road-ward-12 | Vadanappilly AE | |
08 May 2023 | 1.7 % htc connections and 42.07 % pipe laying completed (32 HTC connections completed out of 2218 , 29770M pipe laying completed out of 70765M) | Vadanappilly AE | |
06 May 2023 | 1.7 % htc connections and 41.64 % pipe laying completed (32 HTC connections completed out of 2218 , 29470M pipe laying completed out of 70765M) | Vadanappilly AE | |
05 May 2023 | 1.7% htc connections and 41.36% pipe laying completed (32 HTC connections completed out of 2218 , 29270M pipe laying completed out of 70765M) | Vadanappilly AE | |
04 May 2023 | 1.7% htc connections and 40.37% pipe laying completed (26 HTC connections completed out of 2218 , 28570M pipe laying completed out of 70765M)Eenthakkad road -Ward 10 - 90mm HDPE Pipe laying,Naseeb auditorium Ward 12-160mm HDPE Pipe laying. | Vadanappilly AE | |
03 May 2023 | 1.7 % htc connections and 40 % pipe laying completed (26 HTC connections completed out of 2218 , 28022M pipe laying completed out of 70765M) | Vadanappilly AE | |
02 May 2023 | ward12-Koprakalam Tee road-160mm HDPE Pipe laying,ward 10 -Eenthakkadu road,90 mm HDPE pipe laying,ward2-TKM-Valaparambu road 90mm HDPE Pipe laid,Ward 8 Infront of SNVUP School road 160mm HDPE Pipe laying | Vadanappilly AE | |
29 Apr 2023 | 25 HTC outof 2218 connections completed.W8 Tagore road 110mm HDPE, W13 Nethaji nagar road 90mm HDPE,W12-Aazad nagar road 160 mm HDPE pipe laying. | Vadanappilly AE |