Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 May 2023 | 2.12% htc connections and 45.94% pipe laying completed (40+7/2218 HTC connections completed, 32511M pipe laying completed out of 70765M)TKM-Kacheripadi,Staircase work- reinforcement work on progress. | Vadanappilly AE | |
20 May 2023 | 2.12% htc connections and 45.94% pipe laying completed (40+7/2218 HTC connections completed, 32511M pipe laying completed out of 70765M) | Vadanappilly AE | |
20 May 2023 | 1.8% htc connections and 45.40% pipe laying completed (40+0/2218 HTC connections completed, 32125M pipe laying completed out of 70765M) | Vadanappilly AE | |
18 May 2023 | 1.8% htc connections and 44.94 % pipe laying completed (32+8/2218 HTC connections completed , 31805M pipe laying completed out of 70765M).Ward6 Private mud road-90mm HDPE pipe laying, Ward 11 Punaradhivasa colony road-160mm HDPE pipe laying,Ward 3 Cosmos road-90mm HDPE pipe laying, Kacheripadi-Costruction of staircase-footing started. | Vadanappilly AE | |
17 May 2023 | 1.7 % htc connections and 44.19 % pipe laying completed (32+0/2218 HTC connections completed , 31271M pipe laying completed out of 70765M) | Vadanappilly AE | |
16 May 2023 | 1.7 % htc connections and 43.40 % pipe laying completed (32+0/2218 HTC connections completed , 30714M pipe laying completed out of 70765M) | Vadanappilly AE | |
15 May 2023 | 1.7 % htc connections and 43.22 % pipe laying completed (32+0/2218 HTC connections completed , 30582M pipe laying completed out of 70765M)Ward 11,Thattathodu road-160mm HDPE pipe laying,Ward 6,Health centre road-160mm HDPE pipe laying,Ward 13,Souhridam road-63mm PVC pipe laying. | Vadanappilly AE | |
15 May 2023 | 1.7 % htc connections and 43.22 % pipe laying completed (32+0/2218 HTC connections completed , 30582M pipe laying completed out of 70765M) | Vadanappilly AE | |
12 May 2023 | 1.7 % htc connections and 43 % pipe laying completed (32+0/2218 HTC connections completed , 30432 M pipe laying completed out of 70765M) | Vadanappilly AE | |
11 May 2023 | 1.7 % htc connections and 42.81 % pipe laying completed (32 HTC connections completed out of 2218 , 30294 M pipe laying completed out of 70765M)WARD 16,Pathamkallu thambankadavu beach road 160mm HDPE pipe laying,Thambankadavu beach road 160mm HDPE pipe laid,Ward 11, Thattathodu road -160mm HDPE pipe laying | Vadanappilly AE |