Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Apr 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos Chamber work in progress...Htc and road restoration work in progress... Kollam Project HD
02 Apr 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos Chamber work in progress... Kollam Project HD
01 Apr 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC & Chamber work in progress... Kollam Project HD
31 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC &FHTC work in progress... Chamber work in progress... Kollam Project HD
30 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC &FHTC work in progress... Chamber work in progress... Kollam Project HD
29 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC & Chamber work in progress... Kollam Project HD
28 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC & FHTC work in progress...road restoration work in progress.... Kollam Project HD
27 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos FHTC & HTC work in progress...Chamber work in progress... Kollam Project HD
27 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos. Chamber work in progress.... Kollam Project HD
26 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.leak rectification work in progress.. Kollam Project HD