Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos Chamber work in progress...Htc and road restoration work in progress... | Kollam Project HD | |
02 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos Chamber work in progress... | Kollam Project HD | |
01 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC & Chamber work in progress... | Kollam Project HD | |
31 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC &FHTC work in progress... Chamber work in progress... | Kollam Project HD | |
30 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC &FHTC work in progress... Chamber work in progress... | Kollam Project HD | |
29 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC & Chamber work in progress... | Kollam Project HD | |
28 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.HTC & FHTC work in progress...road restoration work in progress.... | Kollam Project HD | |
27 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos FHTC & HTC work in progress...Chamber work in progress... | Kollam Project HD | |
27 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos. Chamber work in progress.... | Kollam Project HD | |
26 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.leak rectification work in progress.. | Kollam Project HD |