Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4550nos ...Fhtc work in progress... | Kollam Project HD | |
18 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4550nos ...Fhtc and Htc work in progress... | Kollam Project HD | |
17 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4500 nos ...Fhtc and Geo tagging progress... | Kollam Project HD | |
16 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4500 nos ...Fhtc and leak rectification work in progress...Geo tagging progress.... | Kollam Project HD | |
15 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos ...Fhtc and leak rectification work in progress...Geo tagging progress.... | Kollam Project HD | |
14 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos ...Fhtc and leak rectification work in progress...Geo tagging progress.... | Kollam Project HD | |
13 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos ...Fhtc and leak rectification work in progress...Geo tagging progress.... | Kollam Project HD | |
12 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos .Excavation and laying work in progress...Fhtc and htc work in progress...chamber work and excavation and laying work in progress...Geo tagging progress.... | Kollam Project HD | |
11 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos .Excavation and laying work in progress...Fhtc and htc work in progress...chamber work and excavation and laying work in progress...Geo tagging progress.... | Kollam Project HD | |
10 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4418 nos .Excavation and laying work in progress...Fhtc and Geo tagging progress... | Kollam Project HD |