Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4550nos ...Fhtc work in progress... Kollam Project HD
18 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4550nos ...Fhtc and Htc work in progress... Kollam Project HD
17 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4500 nos ...Fhtc and Geo tagging progress... Kollam Project HD
16 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4500 nos ...Fhtc and leak rectification work in progress...Geo tagging progress.... Kollam Project HD
15 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos ...Fhtc and leak rectification work in progress...Geo tagging progress.... Kollam Project HD
14 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos ...Fhtc and leak rectification work in progress...Geo tagging progress.... Kollam Project HD
13 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos ...Fhtc and leak rectification work in progress...Geo tagging progress.... Kollam Project HD
12 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos .Excavation and laying work in progress...Fhtc and htc work in progress...chamber work and excavation and laying work in progress...Geo tagging progress.... Kollam Project HD
11 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4450 nos .Excavation and laying work in progress...Fhtc and htc work in progress...chamber work and excavation and laying work in progress...Geo tagging progress.... Kollam Project HD
10 May 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4418 nos .Excavation and laying work in progress...Fhtc and Geo tagging progress... Kollam Project HD