Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.Htc &..Chamber work in progress... | Kollam Project HD | |
24 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos.Htc &..Chamber work in progress...Road restoration work in progress... | Kollam Project HD | |
23 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 792 .. Total Connection completed 4123nos.Htc &..Chamber work in progress...Road restoration work in progress... | Kollam Project HD | |
22 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 792 .. Total Connection completed 4053 nos..Fhtc & Htc work in progress...Chamber work in progress... | Kollam Project HD | |
21 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 776 ...Htc billed 667Nos Total Connection completed 4027 nos..Fhtc & Htc work in progress...Chamber work in progress... | Kollam Project HD | |
20 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 .HTC completed 667Nos..HTC &. Valve Chamber work in progress... | Kollam Project HD | |
19 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 .HTC completed 667Nos..HTC &. Valve Chamber work in progress... | Kollam Project HD | |
18 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 .HTC completed 667Nos..HTC &. Valve Chamber work in progress... | Kollam Project HD | |
17 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 .HTC completed 766 Nos..HTC &. Chamber work in progress.. | Kollam Project HD | |
16 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 .HTC completed 766 Nos...HTC & Chamber work in progress... | Kollam Project HD |