Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4418 nos ..htc & Laying work in progress...Valve fixing work in progress... | Kollam Project HD | |
08 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4418 nos ..htc & Laying work in progress...Valve fixing work in progress... | Kollam Project HD | |
07 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4418 nos ..fhtc & Laying work in progress... | Kollam Project HD | |
06 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4408 nos ..fhtc & Laying work in progress... | Kollam Project HD | |
05 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4408 nos ..fhtc & Laying work in progress... | Kollam Project HD | |
04 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4095 / 8802 . Total Connection completed 4408 nos ..Htc & Fhtc work in progress... Geotagging progress.... | Kollam Project HD | |
03 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4352 nos ..Htc & Fhtc work in progress... Geotagging progress.... | Kollam Project HD | |
02 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4352 nos ..Htc & Fhtc work in progress... Geotagging progress.... | Kollam Project HD | |
01 May 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4352 nos ..Htc & Fhtc work in progress... Geotagging progress.... | Kollam Project HD | |
29 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4307 nos ..Air valve fixing and fhtc work in progress... | Kollam Project HD |