Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21

Project JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21
Project Code KLMJJM08203262
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 514288000
AS Number .541/2020/WRD Dt:21.08.2020
TS Amount (Rs) 190500000
TS Number TS/2020-2021/2020/16227 Dated: 12-09-2020
Total Bill Submitted (Rs) 135950403
Total Bill Paid (Rs) 135950403
Population Benefitted 44010
Capacity in MLD 5.04
Actual Project Completion Date 30 Sep 2022
Coverage Providing FHTC in Veliyam Grama panchayath (8802 Nos) from existing Scheme and extension during the period of 2020 – 21
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JJM Veliyam-Balance work-Distribution line-Pipeline extension work in ward 1,2,13 and adjoining wards-Pipeline work. Kollam Project Dn
2 JJM-Estimate for providing FHTC in Veliyam Grama panchayath from existing Scheme and extension during the period of 2020 -21 Kollam Project Dn
3 JJM- Veliyam Grama Panchayath - Phase I -Part II-Balance work for pipe line extension and JICA gap closing works Kollam Project Dn
4 PHASE II-Balance FHTCs and water supply to elevated zones- Pipeline Work Kollam Project Dn
5 Phase II works- pipe line extension work and providing 2440 FHTCs -Pipeline Work Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Apr 2024 The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 :- works order to be issued ; 2. Balance works to be arranged for catering water to elevated zones - works estimate submitted for approval Kollam Project HD
10 Apr 2024 The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 :- works order to be issued ; 2. Balance works to be arranged for catering water to elevated zones - works estimate submitted for approval Kollam Project HD
27 Mar 2024 The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 :- works order to be issued ; 2. Balance works to be arranged for catering water to elevated zones - works estimate submitted for approval Kollam Project HD
15 Mar 2024 The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 ; 2. Balance works to be arranged for catering water to elevated zones Kollam Project HD
07 Feb 2024 package 1-Leak rectification progress...,package 2- Work completed and final bill submitted, package3-Successfully commissioned and line charged Kollam Project Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/02/2021
Scheduled date of Completion of the Project 28 Feb 2025
Expected date of Completion 28/02/2025

Processing Dates

AS Date 26 Oct 2023
TS Date 12 Sep 2020

Other details

Project Officers View