Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Apr 2024 The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 :- works order to be issued ; 2. Balance works to be arranged for catering water to elevated zones - works estimate submitted for approval Kollam Project HD
10 Apr 2024 The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 :- works order to be issued ; 2. Balance works to be arranged for catering water to elevated zones - works estimate submitted for approval Kollam Project HD
27 Mar 2024 The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 :- works order to be issued ; 2. Balance works to be arranged for catering water to elevated zones - works estimate submitted for approval Kollam Project HD
15 Mar 2024 The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 ; 2. Balance works to be arranged for catering water to elevated zones Kollam Project HD
07 Feb 2024 package 1-Leak rectification progress...,package 2- Work completed and final bill submitted, package3-Successfully commissioned and line charged Kollam Project Dn EE
13 Sep 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... Kollam Project HD
12 Sep 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... Kollam Project HD
11 Sep 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... Kollam Project HD
05 Sep 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... Kollam Project HD
04 Sep 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... Kollam Project HD