Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Apr 2024 | The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 :- works order to be issued ; 2. Balance works to be arranged for catering water to elevated zones - works estimate submitted for approval | Kollam Project HD | |
10 Apr 2024 | The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 :- works order to be issued ; 2. Balance works to be arranged for catering water to elevated zones - works estimate submitted for approval | Kollam Project HD | |
27 Mar 2024 | The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 :- works order to be issued ; 2. Balance works to be arranged for catering water to elevated zones - works estimate submitted for approval | Kollam Project HD | |
15 Mar 2024 | The Main project consists of works arranged under 2 phases ....Phase I - works arranged as 3 packages for work and 2 for survey works - 100% Completed. Phase 2 Work - includes two works 1. additional distribution works + FHTCs - 2440 ; 2. Balance works to be arranged for catering water to elevated zones | Kollam Project HD | |
07 Feb 2024 | package 1-Leak rectification progress...,package 2- Work completed and final bill submitted, package3-Successfully commissioned and line charged | Kollam Project Dn EE | |
13 Sep 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
12 Sep 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
11 Sep 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
05 Sep 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD | |
04 Sep 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4911 nos...Leak rectification work in progress... | Kollam Project HD |