Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4033 / 8802 ..HTC work progress... | Kollam Project HD | |
04 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4033 / 8802 ..HTC work progress@ ward..12 ..Chamber work progress @ ward 16 | Kollam Project HD | |
03 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4027 / 8802 ..HTC & Leak rectification work in progress... | Kollam Project HD | |
02 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4027 / 8802 ..FHTC & Leak rectification work in progress... | Kollam Project HD | |
01 Mar 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4027 / 8802 ..FHTC & Leak rectification work in progress... Geo tagging progress... | Kollam Project HD | |
28 Feb 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4027 / 8802 ..FHTC &Valve chamber cover slab work in progress... | Kollam Project HD | |
27 Feb 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4027 / 8802 ..FHTC & Leak rectification work in progress.... | Kollam Project HD | |
26 Feb 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4000 / 8802 .. Leak rectification work in progress.... | Kollam Project HD | |
25 Feb 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4000 / 8802 .. Fhtc & Chamber work in progress..Geo tagging progress @ ward 18..Road restoration work in progress.... | Kollam Project HD | |
24 Feb 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4000 / 8802 .. Fhtc work in progress at ward 18.. | Kollam Project HD |