Status Date Overall Project Status Project Officer Contact
15 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4045 / 8802 ..HTC & Chamber work in progress... Kollam Project HD
14 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4045 / 8802 ..HTC & Chamber work in progress... Kollam Project HD
13 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4036 / 8802 ..HTC Work progress at ward 19...Leak rectification work in progress... Kollam Project HD
12 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4036 / 8802 ..HTC Work progress at ward 19...Chember work progress... Kollam Project HD
11 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4036 / 8802 ..HTC Work progress at ward 19...Chember work progress @ward 15 Kollam Project HD
10 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4036 / 8802 ..HTC work in progress& Geo tagging progress... Kollam Project HD
09 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4025 / 8802 ..HTC work in progress& Geo tagging progress... Kollam Project HD
08 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4025 / 8802 ..HTC & Road restoration work in progress... Kollam Project HD
07 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4033 / 8802 ..HTC & Road restoration work in progress... Kollam Project HD
06 Mar 2023 Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4037 / 8802 ..HTC work in progress...@ ward 19 Kollam Project HD