Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4139 nos ....Chamber work , Fhtc in progress.... | Kollam Project HD | |
17 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4139 nos ....Chamber work , Fhtc & htc in progress.... | Kollam Project HD | |
16 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4139 nos ....Chamber work & Fhtc progress.... | Kollam Project HD | |
15 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4139 nos ....Chamber work in progress...52 Htc and Fhtc progress.... | Kollam Project HD | |
14 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4139 nos Chamber work in progress...52 Htc and Fhtc &..chamber work in progress.... | Kollam Project HD | |
13 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4139 nos Chamber work in progress...52 Htc and Fhtc &..chamber work in progress.... | Kollam Project HD | |
12 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4139 nos Chamber work in progress...52 Htc and Fhtc work in progress...chamber work in progress.... | Kollam Project HD | |
10 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4139 nos Chamber work in progress...52 Htc and Fhtc work in progress...chamber work in progress... | Kollam Project HD | |
07 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 4052 / 8802 . Total Connection completed 4139 nos Chamber work in progress...52 Htc and Fhtc work in progress...chamber work in progress... | Kollam Project HD | |
04 Apr 2023 | Veliyam jjm Total supply -75.707 km - completed Laying completed - 74.5 km out of 75.707 km… FHTC completed 3261 / 8802 . FHTC Billed 3261.nos HTC completed 878. Total Connection completed 4139 nos Chamber work in progress...Htc and Fhtc work in progress...chamber work in progress.... | Kollam Project HD |